Developable land
Acquire a fully developable ten-acre parcel within the $25M land ceiling, evidenced by appraisal, ALTA, zoning and route tests.
Invest / Readiness & Risks
Four conditions
These conditions protect the project from treating a concept-level programme as a shovel-ready or revenue-proven asset.
Acquire a fully developable ten-acre parcel within the $25M land ceiling, evidenced by appraisal, ALTA, zoning and route tests.
Secure Phase 1 office and storefront leases with delivery triggers so rent can start when premises are handed over.
Confirm stages, acoustics, capture systems, power and construction fit the management allowances through GMP and vendor bids.
Convert production interest into priced LOIs, anchor bookings and unit economics before stage capital is released.
Next 90 days
Workstreams overlap deliberately so land, design, leasing, operating demand and financing converge into one go / no-go record.
Appoint the owner's representative, brokers, architect and finance-model owner.
Shortlist parcels, test airport routes, build the hotel matrix, request utility letters and interview tenants.
Collect facility quotes, studio interviews, capture proposals, schematic plans and an all-load study.
Integrate the six-year model, anchor LOIs, financing terms and investment-committee decision.
Material risk register
Risk is reduced through gates, not erased. The project should not proceed on any material assumption that has not been assigned, priced and documented.
A ten-acre target is not a controlled parcel. Zoning, access, utilities, fibre, setbacks, acoustic separation and public uses must all work together.
Current figures are management allowances. Land appraisal, GMP, equipment quotes, escalation and financing terms can change the capital requirement.
Signed leases, priced LOIs and anchor bookings must replace market-share assumptions before stage capital is released.
Permits, procurement, power, restaurant inspections, tenant fit-out and specialised hiring can extend the planning windows.